Project: CSO Elimination Program — Storm Sewer Installation
Location (For the remainder of this week and the beginning of next week): 6th Ave between 1st Street and 2nd Street  (anticipated to be complete by Friday), Alley between 1st Street and 2nd Street, 4th Street between 6th Avenue and 5th Avenue, 7th Street between Broadway and 3rd Ave

Start Date: Monday, September 21, 2026
Estimated Duration: Through approximately October 16, weather and site conditions permitting
What to Expect:
  • Construction crews will be installing new storm sewer infrastructure as part of the city’s Combined Sewer Overflow (CSO) elimination program
  • Expect noise, equipment traffic, and temporary parking restrictions in active work areas
  • Access to driveways and businesses will be maintained whenever possible
Background:
This work is part of the city’s critical infrastructure upgrades to manage stormwater runoff and protect Hudson River water quality. Learn more about CSO programs from NYSDEC: https://dec.ny.gov/environmental-protection/water/water-quality/combined-sewer-overflow
Questions or Concerns?
Watervliet City Hall: (518) 270-3800
Email: OfficeoftheGeneralManager@watervlietny.gov