CSO Update: Crew 1 is continuing work on 7th Street between 3rd Ave and 4th Ave
Crew 2 is working at the following locations:
Pedestrian ramp restoration on 3rd Street and 4th Street between Broadway and 1st Avenue.
Pipe installation on 4th Street between 5th Avenue and 6th Avenue next week.
The sidewalk of the alley at 2nd Street is scheduled for next week. Luizzi will begin this work after trash is collected on Tuesday.
Luizzi is planning to perform restoration work on Monday, Columbus Day.
Background:
This work is part of the city’s critical infrastructure upgrades to manage stormwater runoff and protect Hudson River water quality. Learn more about CSO programs from NYSDEC: https://dec.ny.gov/…/water-quality/combined-sewer-overflow
Questions or Concerns?
Watervliet City Hall: (518) 270-3800
Email:OfficeoftheGeneralManager@watervlietny.gov
Updates: https://watervlietny.gov/

See less