As part of the CSO Elimination Phase 2 project, Luizzi is continuing work at the following locations over the next two weeks (November 16 – November 25):
Crew 1 – 5th Street, with ADA ramp work at 4th and 3rd Avenues (Day Work)
  • When: Monday 11/16 through Wednesday 11/25, during normal daytime hours.
  • Crews will be installing storm pipe and structures on 5th Street.
  • Crews will also be preparing for new ADA-accessible curb ramps at the 4th Avenue and 3rd Avenue intersections. Expect sidewalk and crosswalk detours at those corners.
Crew 2 – 7th Street and 6th Avenue (Day Work)
  • When: Monday 11/16 through Wednesday 11/25, during normal daytime hours.
  • Crews will be installing storm pipe and structures and making tie-ins to the existing system at 7th Street and 6th Avenue.
Crew 3 – Saw cutting, Prep, and Restoration (Day Work)
  • Crews will be sawcutting pavement, prepping areas, and restoring surfaces in previously completed work areas during normal daytime hours.
Holiday Schedule:
There will be no construction on Thursday 11/26 or Friday 11/27 for the Thanksgiving holiday. Work will resume Monday 11/30.
What to Expect:
  • Construction crews will be installing new storm sewer infrastructure as part of the city’s Combined Sewer Overflow (CSO) elimination program
  • Expect noise, equipment traffic, and temporary parking restrictions in active work areas
  • Drivers are encouraged to use alternate routes and to follow flagger directions near the work zone.
  • Access to driveways and businesses will be maintained whenever possible
Background:
This work is part of the city’s critical infrastructure upgrades to manage stormwater runoff and protect Hudson River water quality. Learn more about CSO programs from NYSDEC: https://dec.ny.gov/environmental-protection/water/water-quality/combined-sewer-overflow
Questions or Concerns?
Watervliet City Hall: (518) 270-3800
Email: OfficeoftheGeneralManager@watervlietny.gov
Updates: https://watervlietny.gov/