Crew 1 – Road Closure -7th Street between 3rd and 6th Avenues (Day Work)
-
Crews are installing storm pipe and structures.
-
When: Through November 13, during normal daytime hours.
Crew 2 – Road Closure- 5th Street between 3rd and 8th Avenues (Day Work)
-
Crews are installing storm pipe and structures, along with restoration work.
-
When: Through November 13, during normal daytime hours.
Crew 3 – Saw cutting, Topsoil, and Restoration on 5th and 7th Streets (Day Work)
-
Crews will return to previously completed work areas, including 5th and 7th Streets, to sawcut pavement and restore topsoil and surfaces. Residents on blocks where pipe work has already finished may see crews back in front of their homes or businesses for this restoration work.
-
When: Through November 13, during normal daytime hours.
What to Expect:
-
Construction crews will be installing new storm sewer infrastructure as part of the city’s Combined Sewer Overflow (CSO) elimination program
-
Expect noise, equipment traffic, and temporary parking restrictions in active work areas
-
Drivers are encouraged to use alternate routes and to follow flagger directions near the work zone.
-
Access to driveways and businesses will be maintained whenever possible